Eventually, the contractor removed the toilet and bathtub. The toilet relocated to the garage (nothing like getting in and out of the car next to your toilet for a month). The tub suffered from orange spots in the bottom - places where the glaze had become too thin. So we sent it away for re-glazing.
In the shower, plumbing, then valves, then floor tile (not really tile but small, grey pebbles in an epoxy grout), then dry wall appeared.
And there it all sat for a week or so. Finally, a gentle nudge ("Hey, so...this was a 2-week job and we're entering week 4. Any thoughts?" I did not make this call. I was grouchy.) brought a flurry of activity.